The S-Curve is used in development finance to help project managers and lenders to understand the spending patterns of a construction project and to identify any potential cost overruns or delays.
Essentially, the S-Curve refers to a graphical representation of the typical stages of a construction project and is used to show the progress of the project over time and to forecast and track the costs and revenue of a construction project.
It starts with a slow ramp-up of costs as the project is planned and the early stages of construction commence. Costs then increase rapidly as construction progresses and reaches its peak. After the peak, costs start to level off as the project approaches completion and begins to wind down.
By tracking the S-Curve and comparing it to the budget and timeline, lenders can assess the financial health of a project and make decisions about whether to provide further funding or not.
How can I use the S-Curve to calculate my development finance?
Here is how you can use the S-Curve to calculate your development finance:
- Establish a budget: The first step is to establish a budget for your construction project. This should include all costs associated with the project, including materials, labor, and overhead.
- Track progress: As the project progresses, track the actual costs and compare them to the budget. This will help you identify any potential cost overruns or savings.
- Plot the S-Curve: Using the actual costs and the budget, plot the S-curve to show the spending patterns of the project. The S-curve should start with a slow ramp-up of costs, increase rapidly as construction progresses, and level off as the project approaches completion.
- Forecast future costs: Based on the S-curve, you can forecast future costs for the project and identify potential cost overruns. This information can be used to make decisions about whether to provide additional funding or take corrective action to manage costs.
- Monitor cash flow: The S-Curve can also be used to monitor cash flow and to ensure that sufficient funds are available to complete the project. If the project is running behind schedule or over budget, the S-curve can be used to help identify the source of the problem and to make decisions about how to resolve it.
In summary, the S-Curve is a useful tool for calculating development finance by providing a visual representation of the costs and revenue associated with a construction project. By tracking the S-Curve, you can make informed decisions about financing and project management and ensure that sufficient funds are available to complete the project.
Do you help structuring the right finance for your investment or development?
Our funding experts have over 40 years of property experience. We have a profound understanding of the finance process and multi-disciplined investment strategies and know exactly how our funding partners like their cases to be presented.
Reach out if you would like to discuss your deal in more detail.